Kelray Unit Refurbishment

Kelray purchased a new industrial unit in 2013.  Due to the growth and development of the business a larger office space was needed.  The unit was previously used as an electrical wholesaler and it required total refurbishment throughout.  Work included refurbishment to all rooms on the ground floor and the creation of an additional floor to be used as extra office space.  All work to the unit was completed by Kelray employees. 

Front of Unit

Refurbishment of steel cladding to the front of the unit

  • All existing cladding was re-sprayed using a Crown Fast Cladding System
  • Cut out cladding to form window openings
  • Replaced existing timber windows and supplied and fit new PVC windows
  • Installed new automated window shutters to all windows and doors
  • New signage
  • New security alarm system and CCTV.

Reception

Refurbishment was carried out to the reception area

  • Existing wall cladding was removed and replaced with a plaster board and skim finish
  • Installed a fireboard ceiling to meet current building regulations
  • Installed new LED spotlights
  • Replaced existing flooring with Altro multi-screed resin floor
  • Created a curve ceiling to match reception desk
  • Decoration to all walls including a bespoke stainless steel sign

Upstairs Level

We adapted existing mezzanine floor into additional office space

  • Existing staircase was relocated to a more suitable position, providing access to upstairs level
  • Extended mezzanine floor to create extra office space
  • Built metal stud 1- hour fire rated partition walls to segregate offices from storage area
  • Plaster boarded all walls and applied plaster skim finish
  • Installed a new suspended ceiling and LED flat panel lighting
  • New carpet and decoration throughout

Stairs

  • Relocated steel staircase to access upstairs office
  • Built partition wall to create fire break between new offices and the yard
  • Applied non-slip coating
  • Fitted new stainless steel and glass balustrading

 Toilet & Kitchen Area

  • Cut back walls to create a wider corridor
  • Plaster board & plaster skim finish to all walls
  • Fitted new Ash fire doors
  • Decoration and lighting
  • Fitted new toilet and kitchen facilities

Toilet & Kitchen Area Flooring

  • Primed existing concrete floor with Altro Proof Solo Universal DPM
  • Fitted stainless steel trims to create border
  • Laid Altro Multi-Screed flooring
  • Applied 1 coat of Altroseal UVR and 1 coat of Altroseal Clear

Project Title: Kelray Unit Refurbishment

Project Date:  June 2013 - December 2013