Commercial Unit Refurbishment

Project Title: Commercial Unit - Internal and External Refurbishment

Project Date:  August 2013 - November 2013

Project Value: £130,000

Kelray were appointed to complete refurbishment to four industrial units in Swansea.  The units are rented separately by an investment company and they required refurbishment before new occupants could move in.  The project included external works to all units and internal works to the middle units.  All work had to be completed within a two month period as occupants were ready to move in and work had to be completed out of normal working hours as two of the units were already in working operation.   

External works included:

  • Stripped off the existing external cladding of all units and replaced with new cladding
  • Sprayed cladding at the side of the unit to match new cladding at the front of the unit
  • Cut out 3 openings and fitted new Aluminium shopfronts
  • Fitted new overhead sectional doors
  • Installed electrical roller shutters to all windows and doors
  • Created raised platforms to shopfronts
  • Created a disabled access ramp with tactile
  • Replaced all skylights on roof

Internal works included:

  • Cleaned down all internal cladding
  • Decoration to all internal factory block work
  • Refurbishment to offices including decoration and new carpet
  • New vinyl floor to corridors
  • Prepared floors with a diamond grinder and applied high build epoxy paint